Construction Information:
Architect: FFKR
General Contractor: Okland Construction
Product Installed: Gerflor Taraflex 9MM; Game Lines
DesignTeam Project Manager: Matt Dalton
Project information:
65,000 SFT of product in one room.
Over 2.6 miles of game lines were painted
Over 2.8 miles of heat weld was installed
The project was completed in 7 weeks
This project was nominated for Gerflor worldwide project of the year 2010.