BYU Idaho Center, Rexburg Idaho

Construction Information: 

Architect: FFKR

General Contractor: Okland Construction

Product Installed: Gerflor Taraflex 9MM; Game Lines

DesignTeam Project Manager: Matt Dalton

Project information: 

65,000 SFT of product in one room.

Over 2.6 miles of game lines were painted

Over 2.8 miles of heat weld was installed

The project was completed in 7 weeks

 This project was nominated for Gerflor worldwide project of the year 2010.